铝合金导体电缆综合敷设策划

时间:2022-08-26 01:55:04

铝合金导体电缆综合敷设策划

摘要:本文针对污水处理厂铝合金导体电缆外线路由复杂、规格多、截面大的特点,通过施工前进行敷设方案策划,规划敷设相互位置、先后顺序、结构层次等电缆路由,施工过程中按实际需求订购分轴电缆,最终达到布局合理、美观的要求,避免了电缆敷设交叉、接头及浪费问题。

关键词:电缆敷设;方案策划;避免交叉;美观;质量;工期

Abstract: this article in view of the sewage treatment plant of aluminum alloy conductor cable complicated perimeter routing, more specifications, of the characteristics of big cross section through the laying scheme planning before construction, planning, installation position, sequence and structure layer of cable routing, order points, axis of cable construction process according to the actual demand, finally reached the requirements of layout is reasonable, beautiful, avoids the problems of cable laying, joint and waste.

Key words: cable laying; The project plan; Avoid cross; Is beautiful; Quality; Time limit for a project

中图分类号:TM757 文献标识码:A文章编号:2095-2104(2013)07-0056-01

0 引言

某污水处理及再生水利用工程,全场共计33个装置区,布局分散。动力电缆采用新型材料—铝合金导体电缆12.6万米、控制及通讯11万米。

污水厂具有电缆规格多、截面大,新工艺、敷设面积大路由复杂且分散等特点,往往导致施工中电缆敷设经常出现电缆交叉、电缆余量不易控制等情况。电缆交叉容易造成因发热产生电缆故障点,并影响其美观和故障排除,为日后运行安全及电缆维护造成困难。

为了解决以上问题,对全厂电缆统一分析,进行了施工前期的敷设方案策划,规划了敷设相互位置、先后顺序、结构层次等电缆路由,有效的解决了以上问题。

1 熟悉图纸,绘制全厂电缆沟示意图

在认真熟悉、审核施工图纸,领会设计意图后。绘制出全厂的电缆沟示意图。

2 区域电缆敷设策划

按照图纸要求、走向及距离,分系统编制电缆敷设清册。

按电压等级、功能划分、电缆粗细、敷设顺序进行某区域电缆敷设规划,为了避免电缆交叉,达到布置美观,铺设方便的目的,把电缆和桥架安放在合理的层次上,绘制区域电缆沟示意图和电缆沟断面布置图。例如:501总变站至粗细格栅、进水泵房、初沉池、初沉池污泥泵房、反应池的电缆敷设。各种规格的电缆45000米。

电缆沟分段图例

电缆沟断面布置图

3 汇总各区域电缆布置图,按设计和现场实际路径计算和测量每根电缆实际需用长度,以减少电缆接头和余量,形成电缆综合敷设施工方案并经审核。

4 按实际需用长度订购分轴电缆,安排专人按计划对电缆轴进行分配,避免了电缆混用、长电缆短用、不必要的接头问题,降低了施工成本,提高安全性。

5 确定各个区域施工负责人,严格按施工方案进行施工。

6、结束语

通过前期电缆综合敷设策划,虽然增加了技术人员的工作量,但在施工过程中,避免了电缆敷设交叉问题,达到了布局合理、美观的要求;极大的提高工程质量及减少电缆余量,提高敷设工作效率、缩短了施工周期、降低了施工成本,从而取得了显著的经济效益。